Risk Analytics
Advanced statistical insights and early warning systems.
Critical Alerts
15
Immediate Action Required
High Risk Alerts
15
Close Monitoring Advised
Avg Cost Overrun (Critical)
₹121 Cr
Per Project Estimate
Avg Schedule Delay
41 Months
Predicted deviation
Top Risk Drivers
Primary factors causing Critical delays
Critical Risks by Sector
Proportional distribution of critical alerts
Critical Project Alerts
Detailed register of projects requiring immediate intervention.
| Project Name | Agency | Primary Risk Driver | Pred. Overrun | Delay | Score |
|---|---|---|---|---|---|
| Thorapalli - Agraharam - Jittandahalli Section from km 23.350 to km 60.100 [Hosur to | Dhamrapuri Pkg-2] | Noticeable Cost Overrun Trajectory | +₹273 Cr | +23M | 87 |
| Construction of Kaithi-Padaria Kala bypass, Patna-Tamoli bypass, Jaso bypass and | Nagod bypass total length 15.44 Km to 2-lane with paved shoulders flexible | Noticeable Cost Overrun Trajectory | +₹31 Cr | +35M | 83 |
| Amritsarairport Junction - Ramdas from km. 100.835 to km. 139.813 Pkg - IV | NHAI | Noticeable Cost Overrun Trajectory | +₹80 Cr | +51M | 87 |
| Widening to intermediate/two lane to 2 lane with paved shoulder from Existing | chanages Km 112.750 to 142.00 Liingasur to Mudabal cross & from Km. 147.070 to | Noticeable Cost Overrun Trajectory | +₹42 Cr | +51M | 86 |
| Akkalkot MH/KN border New Greenfield corridor from Km 512.000 to Km 548.400 of | NH-150C part of Akkalkot KN/TS Border section Package XIV | Noticeable Cost Overrun Trajectory | +₹233 Cr | +19M | 81 |
| Widening & Upgradation to four lane configuration from Km.34.900 Bhadohi to | km.73.134 Jaunpur of NH-135A on EPC mode | Noticeable Cost Overrun Trajectory | +₹32 Cr | +24M | 85 |
| 4/6L Greenfield LudhianaRupnagar highway from Jn. with NE-5 village near to | ManewalLudhiana to Jn. with NH-205 near Bheora Village Rupnagar from Km 66.0 to | Noticeable Cost Overrun Trajectory | +₹85 Cr | +44M | 93 |
| Balance work of Construction of Ring Road for Raebareli City on eastern side of NH- | 24B Phase-1 on EPC mode. | Noticeable Cost Overrun Trajectory | +₹59 Cr | +45M | 90 |
| Integrated Command control Center [ICCC] - Construction and Development of | Integrated Command Control Center with Security, Surveillance, ITMS, Connecting | Noticeable Cost Overrun Trajectory | +₹25 Cr | +60M | 93 |
| 6L Amritsar-Bathinda Greenfield section from village Tiba on NE-5A to Jn. with Moga | Jalandhar road NH-703 near Dharamkot from km 0.000 to km 39.000 of NH-754A | Noticeable Cost Overrun Trajectory | +₹249 Cr | +35M | 82 |
| Sheohar-Sitamarhi Section km 40.000 to 79.400 km Lot-I | MoRTH | Noticeable Cost Overrun Trajectory | +₹33 Cr | +54M | 89 |
| 4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 to Gaju Village at Km | 32.982 of NH-530B Pkg-IB | Noticeable Cost Overrun Trajectory | +₹323 Cr | +41M | 93 |
| Rehabilitation & Upgradation of NH214 New NH-216 from Km 34/230 to Km 84/550 | Losari to Machavaram Section to two lane with paved shoulder in the state of | Moderate Budget Utilization Inefficiency | +₹74 Cr | +54M | 88 |
| Moga - Bagha Purana - Bajakhana from km. 0.00 to km. 43.32 | NHAI | Noticeable Cost Overrun Trajectory | +₹204 Cr | +42M | 88 |
| Construction of 2-laning with Hard shoulder road of Ukhrul - Tolloi - Tadubi section of | NH-102A from Design Chainage 81.870 km to 105.825 km in the State of Manipur on | Noticeable Cost Overrun Trajectory | +₹74 Cr | +35M | 94 |