Project ID: 619147Sector: Urban Development

4L of Bal Works of Mahuva to Kagvadar from 100.450 Km. to 140.470 Km. of NH-8E

Implementing Agency: Pkg- III
Project Overview
Core details and current status.
Agency
Pkg- III
State
Gujarat
Approval
08/2020 | (03/2021)
Target DoC
2022-09-01
Physical Progress
99.71%
x
Risk Assessment
66
High Risk
Predicted Delay+34 Months
Predicted Overrun+₹99.26 Cr
Financial Status
Original Cost₹603.08 Cr
Revised Cost ₹628.49 Cr
Cumulative Expenditure₹624.41 Cr
x
99.4% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Significant Schedule Slip (+34 Months)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+34 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.