Project ID: 705515Sector: Urban Development

Budhapank-Salegaon via Rajatgarh - 3rd & 4th line 85 85 km

Implementing Agency: CAO/C/ECOR ECoR mor
Project Overview
Core details and current status.
Agency
CAO/C/ECOR ECoR mor
State
Odisha
Approval
12/2015 | (04/2016)
Target DoC
2026-03-01
Physical Progress
86%
x
Risk Assessment
90
Critical Risk
Predicted Delay+32 Months
Predicted Overrun+₹138.41 Cr
Financial Status
Original Cost₹1,173.00 Cr
Revised Cost ₹3,034.80 Cr
Cumulative Expenditure₹2,213.72 Cr
x
72.9% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Significant Schedule Slip (+32 Months)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+32 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.