Project ID: 705629Sector: Railways

Narayangarh - Bhadrak - 3rd line 155 km

Implementing Agency: CAO/C/SER SER mor
Project Overview
Core details and current status.
Agency
CAO/C/SER SER mor
State
Multi-States (Odisha, West Bengal)
Approval
03/2019 | (02/2020)
Target DoC
2025-12-01
Physical Progress
84%
x
Risk Assessment
85
Critical Risk
Predicted Delay+40 Months
Predicted Overrun+₹232.90 Cr
Financial Status
Original Cost₹2,400.00 Cr
Revised Cost ₹3,425.32 Cr
Cumulative Expenditure₹2,886.02 Cr
x
84.3% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Extreme Schedule Delay Predicted (+40 Months)
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+40 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.