Project Overview
Core details and current status.
Agency
Krishnanagar-Chartala, MM for Krishnanagar-Chapra-NL, Naihati-Ranaghat-3rd line,
State
Chhattisgarh
Approval
07/2015 | (12/2005)
Target DoC
2027-02-01
Physical Progress
49%
x
Risk Assessment
84
Critical RiskPredicted Delay+46 Months
Predicted Overrun+₹95.29 Cr
Financial Status
Original Cost₹1,000.00 Cr
Revised Cost ₹2,153.91 Cr
Cumulative Expenditure₹925.70 Cr
x
43.0% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Coal projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Coal projects.
- Extreme Schedule Delay Predicted (+46 Months)Historically accounts for 30-40% of schedule deviations in similar Coal projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+46 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.