Project Overview
Core details and current status.
Agency
NHAI
State
Multi-States (Karnataka, Kerala)
Approval
05/2020 | (11/2021)
Target DoC
2024-05-01
Physical Progress
100%
x
Risk Assessment
63
High RiskPredicted Delay+31 Months
Predicted Overrun+₹127.33 Cr
Financial Status
Original Cost₹1,981.07 Cr
Revised Cost ₹2,681.48 Cr
Cumulative Expenditure₹1,701.33 Cr
x
63.4% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Energy projects.
- Significant Schedule Slip (+31 Months)Historically accounts for 30-40% of schedule deviations in similar Energy projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+31 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.