Project Overview
Core details and current status.
Agency
NHAI
State
Chhattisgarh
Approval
12/2015 | (01/2018)
Target DoC
2020-07-01
Physical Progress
99.85%
x
Risk Assessment
61
High RiskPredicted Delay+19 Months
Predicted Overrun+₹89.06 Cr
Financial Status
Original Cost₹1,659.12 Cr
Revised Cost ₹1,622.49 Cr
Cumulative Expenditure₹1,546.89 Cr
x
95.3% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Telecommunication projects.
- Significant Schedule Slip (+19 Months)Historically accounts for 30-40% of schedule deviations in similar Telecommunication projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+19 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.