Project Overview
Core details and current status.
Agency
MinistryofPetroleumNaturalGas
State
Tamil Nadu
Approval
11/2012 | (11/2012)
Target DoC
2017-02-01
Physical Progress
86.4%
x
Risk Assessment
90
Critical RiskPredicted Delay+54 Months
Predicted Overrun+₹60.51 Cr
Financial Status
Original Cost₹678.00 Cr
Revised Cost ₹1,732.00 Cr
Cumulative Expenditure₹1,206.36 Cr
x
69.7% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Water Resources projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Water Resources projects.
- Extreme Schedule Delay Predicted (+54 Months)Historically accounts for 30-40% of schedule deviations in similar Water Resources projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+54 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.