Project Overview
Core details and current status.
Agency
CAOC/NER NER mor
State
Multi-States (Bihar, Uttar Pradesh)
Approval
03/2013 | (12/2015)
Target DoC
2025-02-01
Physical Progress
95%
x
Risk Assessment
89
Critical RiskPredicted Delay+47 Months
Predicted Overrun+₹100.70 Cr
Financial Status
Original Cost₹963.00 Cr
Revised Cost ₹1,010.84 Cr
Cumulative Expenditure₹1,000.05 Cr
x
98.9% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Extreme Schedule Delay Predicted (+47 Months)Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Multiple Historical Bottlenecks Identified in RegionHistorically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+47 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.