Dum Dum Airport-New Garia via Rajarhat-Construction of Metro Railway

Implementing Agency: RVNL - II
Project Overview
Core details and current status.
Agency
RVNL - II
State
West Bengal
Approval
03/2010 | (10/2011)
Target DoC
2025-12-01
Physical Progress
87%
x
Risk Assessment
71
High Risk
Predicted Delay+17 Months
Predicted Overrun+₹1,532.17 Cr
Financial Status
Original Cost₹8,964.00 Cr
Revised Cost ₹8,964.00 Cr
Cumulative Expenditure₹8,984.66 Cr
x
100.2% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Significant Schedule Slip (+17 Months)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+17 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.