Project ID: 705391Sector: Steel

Jiribam-Imphal 110 km

Implementing Agency: CAO/C-III/NFR NFR mor
Project Overview
Core details and current status.
Agency
CAO/C-III/NFR NFR mor
State
Chhattisgarh
Approval
10/2003 | (04/2009)
Target DoC
2026-12-01
Physical Progress
78%
x
Risk Assessment
80
Critical Risk
Predicted Delay+38 Months
Predicted Overrun+₹1,557.86 Cr
Financial Status
Original Cost₹14,323.00 Cr
Revised Cost ₹21,886.00 Cr
Cumulative Expenditure₹16,931.50 Cr
x
77.4% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Steel projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Steel projects.
  • Extreme Schedule Delay Predicted (+38 Months)
    Historically accounts for 30-40% of schedule deviations in similar Steel projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+38 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.