Project ID: 618862Sector: Urban Development

Bakhtiyarpur-Rajauli Pkg-III from km. 101.630 to km.152.520

Implementing Agency: NHAI
Project Overview
Core details and current status.
Agency
NHAI
State
Bihar
Approval
09/2020 | (12/2021)
Target DoC
2024-06-01
Physical Progress
99.14%
x
Risk Assessment
64
High Risk
Predicted Delay+35 Months
Predicted Overrun+₹102.22 Cr
Financial Status
Original Cost₹2,156.22 Cr
Revised Cost ₹3,046.61 Cr
Cumulative Expenditure₹1,818.91 Cr
x
59.7% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Significant Schedule Slip (+35 Months)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+35 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.