Project Overview
Core details and current status.
Agency
NHAI
State
Bihar
Approval
09/2020 | (12/2021)
Target DoC
2024-06-01
Physical Progress
99.14%
x
Risk Assessment
64
High RiskPredicted Delay+35 Months
Predicted Overrun+₹102.22 Cr
Financial Status
Original Cost₹2,156.22 Cr
Revised Cost ₹3,046.61 Cr
Cumulative Expenditure₹1,818.91 Cr
x
59.7% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Significant Schedule Slip (+35 Months)Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+35 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.