Project Overview
Core details and current status.
Agency
RVNL - II
State
West Bengal
Approval
03/2010 | (04/2010)
Target DoC
2026-12-01
Physical Progress
51%
x
Risk Assessment
77
High RiskPredicted Delay+23 Months
Predicted Overrun+₹697.27 Cr
Financial Status
Original Cost₹4,835.00 Cr
Revised Cost ₹10,362.00 Cr
Cumulative Expenditure₹5,098.73 Cr
x
49.2% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Significant Schedule Slip (+23 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+23 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.