Project Overview
Core details and current status.
Agency
Irrigation and CAD-TG
State
Odisha
Approval
04/2003 | (01/2004)
Target DoC
2019-12-01
Physical Progress
79.5%
x
Risk Assessment
91
Critical RiskPredicted Delay+33 Months
Predicted Overrun+₹65.69 Cr
Financial Status
Original Cost₹989.43 Cr
Revised Cost ₹2,301.28 Cr
Cumulative Expenditure₹2,804.16 Cr
x
121.9% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Significant Schedule Slip (+33 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+33 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.