Project ID: 705359Sector: Water Resources

Talcher-Bimlagarh 154 km

Implementing Agency: CAO/C/ECOR ECoR mor
Project Overview
Core details and current status.
Agency
CAO/C/ECOR ECoR mor
State
Odisha
Approval
03/2004 | (07/2008)
Target DoC
2025-03-01
Physical Progress
56%
x
Risk Assessment
89
Critical Risk
Predicted Delay+37 Months
Predicted Overrun+₹142.51 Cr
Financial Status
Original Cost₹1,928.00 Cr
Revised Cost ₹4,546.84 Cr
Cumulative Expenditure₹2,164.01 Cr
x
47.6% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Water Resources projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Water Resources projects.
  • Extreme Schedule Delay Predicted (+37 Months)
    Historically accounts for 30-40% of schedule deviations in similar Water Resources projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+37 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.