Project Overview
Core details and current status.
Agency
CAO/C-II/NFR NFR mor
State
Multi-States (Bihar, West Bengal)
Approval
08/2022 | (10/2023)
Target DoC
2027-08-01
Physical Progress
65%
x
Risk Assessment
76
High RiskPredicted Delay+39 Months
Predicted Overrun+₹165.29 Cr
Financial Status
Original Cost₹942.64 Cr
Revised Cost ₹1,961.00 Cr
Cumulative Expenditure₹952.95 Cr
x
48.6% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Energy projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Energy projects.
- Extreme Schedule Delay Predicted (+39 Months)Historically accounts for 30-40% of schedule deviations in similar Energy projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+39 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.