Project ID: 618921Sector: Railways

4L of Kathlighat to Shakral Village from Km 128.835 to Km 146.300 of NH- 5 Shimla

Implementing Agency: Bypass - Pkg I
Project Overview
Core details and current status.
Agency
Bypass - Pkg I
State
Himachal Pradesh
Approval
03/2022 | (04/2023)
Target DoC
2026-04-01
Physical Progress
64.2%
x
Risk Assessment
66
High Risk
Predicted Delay+13 Months
Predicted Overrun+₹147.85 Cr
Financial Status
Original Cost₹1,703.48 Cr
Revised Cost ₹2,648.80 Cr
Cumulative Expenditure₹1,182.61 Cr
x
44.6% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Significant Schedule Slip (+13 Months)
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+13 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.