Project Overview
Core details and current status.
Agency
Bypass - Pkg I
State
Himachal Pradesh
Approval
03/2022 | (04/2023)
Target DoC
2026-04-01
Physical Progress
64.2%
x
Risk Assessment
66
High RiskPredicted Delay+13 Months
Predicted Overrun+₹147.85 Cr
Financial Status
Original Cost₹1,703.48 Cr
Revised Cost ₹2,648.80 Cr
Cumulative Expenditure₹1,182.61 Cr
x
44.6% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Significant Schedule Slip (+13 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+13 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.