Project Overview
Core details and current status.
Agency
CAOC/CR CR mor
State
Maharashtra
Approval
02/1999 | (12/2003)
Target DoC
2027-03-01
Physical Progress
60%
x
Risk Assessment
88
Critical RiskPredicted Delay+42 Months
Predicted Overrun+₹26.41 Cr
Financial Status
Original Cost₹138.48 Cr
Revised Cost ₹1,790.50 Cr
Cumulative Expenditure₹1,132.25 Cr
x
63.2% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Road Transport projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Road Transport projects.
- Extreme Schedule Delay Predicted (+42 Months)Historically accounts for 30-40% of schedule deviations in similar Road Transport projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+42 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.