Project ID: 705357Sector: Road Transport

Baramati - Lonand 54 km

Implementing Agency: CAOC/CR CR mor
Project Overview
Core details and current status.
Agency
CAOC/CR CR mor
State
Maharashtra
Approval
02/1999 | (12/2003)
Target DoC
2027-03-01
Physical Progress
60%
x
Risk Assessment
88
Critical Risk
Predicted Delay+42 Months
Predicted Overrun+₹26.41 Cr
Financial Status
Original Cost₹138.48 Cr
Revised Cost ₹1,790.50 Cr
Cumulative Expenditure₹1,132.25 Cr
x
63.2% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Road Transport projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Road Transport projects.
  • Extreme Schedule Delay Predicted (+42 Months)
    Historically accounts for 30-40% of schedule deviations in similar Road Transport projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+42 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.