Project Overview
Core details and current status.
Agency
CAO/Con/North/MHX ECR mor
State
Bihar
Approval
10/2007 | (12/2008)
Target DoC
2020-03-01
Physical Progress
74%
x
Risk Assessment
89
Critical RiskPredicted Delay+25 Months
Predicted Overrun+₹173.92 Cr
Financial Status
Original Cost₹2,067.00 Cr
Revised Cost ₹3,991.33 Cr
Cumulative Expenditure₹2,843.39 Cr
x
71.2% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Significant Schedule Slip (+25 Months)Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+25 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.