Project ID: 400187Sector: Coal

INTEGRATED LAKHANPUR-BELPAHAR-

Implementing Agency: MCL - CIL
Project Overview
Core details and current status.
Agency
MCL - CIL
State
Chhattisgarh
Approval
05/2018 | (05/2018)
Target DoC
2027-03-01
Physical Progress
82.9%
x
Risk Assessment
74
High Risk
Predicted Delay+42 Months
Predicted Overrun+₹403.11 Cr
Financial Status
Original Cost₹2,434.75 Cr
Revised Cost ₹2,434.75 Cr
Cumulative Expenditure₹2,133.70 Cr
x
87.6% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Coal projects.
  • Extreme Schedule Delay Predicted (+42 Months)
    Historically accounts for 30-40% of schedule deviations in similar Coal projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+42 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.