Project Overview
Core details and current status.
Agency
MCL - CIL
State
Odisha
Approval
11/2018 | (11/2018)
Target DoC
2029-03-01
Physical Progress
53.54%
x
Risk Assessment
64
High RiskPredicted Delay+17 Months
Predicted Overrun+₹436.78 Cr
Financial Status
Original Cost₹2,838.86 Cr
Revised Cost ₹2,838.86 Cr
Cumulative Expenditure₹1,716.58 Cr
x
60.5% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Significant Schedule Slip (+17 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+17 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.