Project ID: 705735Sector: Healthcare

Solapur-Osmanabad - New line via Tuljapur 84.44 km umbrella work PB23/2018-

Implementing Agency: 19/NR
Project Overview
Core details and current status.
Agency
19/NR
State
Chhattisgarh
Approval
01/2019 | (09/2024)
Target DoC
2027-03-01
Physical Progress
22%
x
Risk Assessment
70
High Risk
Predicted Delay+20 Months
Predicted Overrun+₹108.23 Cr
Financial Status
Original Cost₹904.92 Cr
Revised Cost ₹1,647.87 Cr
Cumulative Expenditure₹1,202.73 Cr
x
73.0% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Healthcare projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Healthcare projects.
  • Significant Schedule Slip (+20 Months)
    Historically accounts for 30-40% of schedule deviations in similar Healthcare projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+20 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.