Project Overview
Core details and current status.
Agency
19/NR
State
Chhattisgarh
Approval
01/2019 | (09/2024)
Target DoC
2027-03-01
Physical Progress
22%
x
Risk Assessment
70
High RiskPredicted Delay+20 Months
Predicted Overrun+₹108.23 Cr
Financial Status
Original Cost₹904.92 Cr
Revised Cost ₹1,647.87 Cr
Cumulative Expenditure₹1,202.73 Cr
x
73.0% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Healthcare projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Healthcare projects.
- Significant Schedule Slip (+20 Months)Historically accounts for 30-40% of schedule deviations in similar Healthcare projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+20 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.