Project Overview
Core details and current status.
Agency
State of Odisha
State
Odisha
Approval
10/2017 | (01/2018)
Target DoC
2020-07-01
Physical Progress
99%
x
Risk Assessment
89
Critical RiskPredicted Delay+42 Months
Predicted Overrun+₹154.00 Cr
Financial Status
Original Cost₹999.32 Cr
Revised Cost ₹1,178.31 Cr
Cumulative Expenditure₹1,128.52 Cr
x
95.8% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Extreme Schedule Delay Predicted (+42 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
- Multiple Historical Bottlenecks Identified in RegionHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+42 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.