Project ID: 619119Sector: Railways

Cuttack-Angul Section of NH-42 New NH-55 from km 0.400 to km 60.200 Pkg-I in the

Implementing Agency: State of Odisha
Project Overview
Core details and current status.
Agency
State of Odisha
State
Odisha
Approval
10/2017 | (01/2018)
Target DoC
2020-07-01
Physical Progress
99%
x
Risk Assessment
89
Critical Risk
Predicted Delay+42 Months
Predicted Overrun+₹154.00 Cr
Financial Status
Original Cost₹999.32 Cr
Revised Cost ₹1,178.31 Cr
Cumulative Expenditure₹1,128.52 Cr
x
95.8% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Extreme Schedule Delay Predicted (+42 Months)
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Multiple Historical Bottlenecks Identified in Region
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+42 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.