Project Overview
Core details and current status.
Agency
NHAI
State
Jharkhand
Approval
02/2017 | (11/2019)
Target DoC
2024-08-01
Physical Progress
98.5%
x
Risk Assessment
86
Critical RiskPredicted Delay+35 Months
Predicted Overrun+₹43.09 Cr
Financial Status
Original Cost₹662.44 Cr
Revised Cost ₹826.59 Cr
Cumulative Expenditure₹825.20 Cr
x
99.8% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Moderate Budget Utilization InefficiencyHistorically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Significant Schedule Slip (+35 Months)Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+35 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.