Project ID: 618863Sector: Urban Development

Barhi-Koderma Section of NH31 km 0.00 - km 27.5

Implementing Agency: NHAI
Project Overview
Core details and current status.
Agency
NHAI
State
Jharkhand
Approval
02/2017 | (11/2019)
Target DoC
2024-08-01
Physical Progress
98.5%
x
Risk Assessment
86
Critical Risk
Predicted Delay+35 Months
Predicted Overrun+₹43.09 Cr
Financial Status
Original Cost₹662.44 Cr
Revised Cost ₹826.59 Cr
Cumulative Expenditure₹825.20 Cr
x
99.8% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Moderate Budget Utilization Inefficiency
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Significant Schedule Slip (+35 Months)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+35 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.