Project Overview
Core details and current status.
Agency
National Hydroelectric Power Corporation Limited [NHPC]
State
Multi-States (Arunachal Pradesh, Assam)
Approval
09/2003 | (01/2005)
Target DoC
2010-09-01
Physical Progress
97.98%
x
Risk Assessment
84
Critical RiskPredicted Delay+29 Months
Predicted Overrun+₹949.35 Cr
Financial Status
Original Cost₹6,285.33 Cr
Revised Cost ₹26,075.54 Cr
Cumulative Expenditure₹26,448.07 Cr
x
101.4% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Significant Schedule Slip (+29 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+29 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.