Project Overview
Core details and current status.
Agency
km]
State
Maharashtra
Approval
02/1997 | (04/2013)
Target DoC
2026-12-01
Physical Progress
93%
x
Risk Assessment
92
Critical RiskPredicted Delay+37 Months
Predicted Overrun+₹509.32 Cr
Financial Status
Original Cost₹2,538.67 Cr
Revised Cost ₹5,942.48 Cr
Cumulative Expenditure₹5,054.69 Cr
x
85.1% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Extreme Schedule Delay Predicted (+37 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+37 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.