Project Overview
Core details and current status.
Agency
Department of Water Resources-PB
State
Chhattisgarh
Approval
02/2010 | (04/2018)
Target DoC
2022-06-01
Physical Progress
88%
x
Risk Assessment
87
Critical RiskPredicted Delay+43 Months
Predicted Overrun+₹207.41 Cr
Financial Status
Original Cost₹2,285.81 Cr
Revised Cost ₹2,715.70 Cr
Cumulative Expenditure₹2,201.94 Cr
x
81.1% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Roads & Highways projects.
- Extreme Schedule Delay Predicted (+43 Months)Historically accounts for 30-40% of schedule deviations in similar Roads & Highways projects.
- Multiple Historical Bottlenecks Identified in RegionHistorically accounts for 30-40% of schedule deviations in similar Roads & Highways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+43 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.