Project ID: 705394Sector: Railways

Teteliya-Byrnihat 21.5 km

Implementing Agency: CAO/C-II/NFR NFR mor
Project Overview
Core details and current status.
Agency
CAO/C-II/NFR NFR mor
State
Multi-States (Assam, Meghalaya)
Approval
11/2006 | (04/2011)
Target DoC
2011-11-01
Physical Progress
87%
x
Risk Assessment
88
Critical Risk
Predicted Delay+60 Months
Predicted Overrun+₹200.78 Cr
Financial Status
Original Cost₹1,304.62 Cr
Revised Cost ₹1,432.14 Cr
Cumulative Expenditure₹1,272.35 Cr
x
88.8% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Extreme Schedule Delay Predicted (+60 Months)
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Multiple Historical Bottlenecks Identified in Region
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+60 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.