Project Overview
Core details and current status.
Agency
NHAI
State
Bihar
Approval
12/2015 | (06/2017)
Target DoC
2019-12-01
Physical Progress
99.95%
x
Risk Assessment
61
High RiskPredicted Delay+22 Months
Predicted Overrun+₹167.30 Cr
Financial Status
Original Cost₹1,898.84 Cr
Revised Cost ₹1,898.84 Cr
Cumulative Expenditure₹1,799.23 Cr
x
94.8% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Significant Schedule Slip (+22 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+22 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.