Project ID: 619073Sector: Urban Development

4L of 42.000 to km 80.00 of Dodaballapur Bypass to Hoskote section of NH-648 Old

Implementing Agency: NH-207 [Bangalore Ring Road Pkg 2]
Project Overview
Core details and current status.
Agency
NH-207 [Bangalore Ring Road Pkg 2]
State
Karnataka
Approval
02/2020 | (02/2021)
Target DoC
2023-02-01
Physical Progress
99.2%
x
Risk Assessment
76
High Risk
Predicted Delay+43 Months
Predicted Overrun+₹184.33 Cr
Financial Status
Original Cost₹1,317.74 Cr
Revised Cost ₹1,846.52 Cr
Cumulative Expenditure₹1,367.20 Cr
x
74.0% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Extreme Schedule Delay Predicted (+43 Months)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+43 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.