Project Overview
Core details and current status.
Agency
NH-207 [Bangalore Ring Road Pkg 2]
State
Karnataka
Approval
02/2020 | (02/2021)
Target DoC
2023-02-01
Physical Progress
99.2%
x
Risk Assessment
76
High RiskPredicted Delay+43 Months
Predicted Overrun+₹184.33 Cr
Financial Status
Original Cost₹1,317.74 Cr
Revised Cost ₹1,846.52 Cr
Cumulative Expenditure₹1,367.20 Cr
x
74.0% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Extreme Schedule Delay Predicted (+43 Months)Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+43 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.