Official Reports & Analytics

Downloadable statistical summaries and AI-generated project risk reports.

Monthly Flash Report
Comprehensive overview of 177 central sector projects.

Total Approved Cost

₹655,122.95 Cr

Total Projects

177

Exception Report (Critical Risks)
Detailed list of 43 projects with severe predicted delays.

Avg Cost Overrun

+₹195 Cr

Avg Schedule Delay

+19 Months

Infrastructure Projects Database
Live tabular view of all monitored central sector projects.
Project NameAgencySectorRisk ScoreStatus
Kanupur Irrigation ProjectIrrigation and CAD-TGRailways91/100Critical
Wardha-Nagpur - 4th line 78.70 kmCAOC/CR CR morRailways89/100Critical
Dallirajhara - Rowghat New Rail Line Project, Phase-IRail Vikas Nigam LimitedUrban Development92/100Critical
Sulwade-Jamphal-Kanoli Lift Irrigation SchemeDepartment of water resources-MH - IIRailways85/100Critical
Chhapra-Ballia - Patch doubling 65 kmCAOC/NER NER morUrban Development89/100Critical
Barhi-Koderma Section of NH31 km 0.00 - km 27.5NHAIUrban Development86/100Critical
Ghatampur Thermal Power Plant 3 X 660 MWNLC India Limited [NLCIL]Water Resources83/100Critical
Nerchowk km 190.000 to Pandoh including Pandoh bypass km221.305NHAIRailways86/100Critical
Aruna Medium Irrigation ProjectDepartment of water resources-MH - IIRoad Transport87/100Critical
Ahmednagar - Beed - Parli - Vaijnath New Broad Gauge Line Railway Project [261.3km]Railways92/100Critical
Narayangarh - Bhadrak - 3rd line 155 kmCAO/C/SER SER morRailways85/100Critical
Solan - Kaithlighat Section of NH-22 Now NH-5 from Km. 106.139 to Km.129.05NHAIRailways89/100Critical
Mumbai Metro Line 3Mumbai Metro Rail Corporation Limited [MMRC]Road Transport80/100Critical
Hajipur-Sagauli via Vaishali 148.3 kmCAO/Con/North/MHX ECR morUrban Development89/100Critical
Poly Butadiene Rubber plant at PanipatIndian Oil Corporation Limited [IOCL]Energy82/100Critical
Showing top 15 of 177 projects. Export CSV to view all.