Project ID: 705583Sector: Energy

Anand Vihar-Tilak Bridge - 3rd & 4th line 9.77 km

Implementing Agency: CAOC/NR NR mor
Project Overview
Core details and current status.
Agency
CAOC/NR NR mor
State
Delhi
Approval
06/2012 | (04/2014)
Target DoC
2023-03-01
Physical Progress
23%
x
Risk Assessment
60
High Risk
Predicted Delay+29 Months
Predicted Overrun+₹94.19 Cr
Financial Status
Original Cost₹667.00 Cr
Revised Cost ₹701.88 Cr
Cumulative Expenditure₹393.68 Cr
x
56.1% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Energy projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Energy projects.
  • Significant Schedule Slip (+29 Months)
    Historically accounts for 30-40% of schedule deviations in similar Energy projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+29 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.