Project Overview
Core details and current status.
Agency
Water Resources-AP
State
Andhra Pradesh
Approval
01/2009 | (11/2009)
Target DoC
2022-04-01
Physical Progress
86.15%
x
Risk Assessment
83
Critical RiskPredicted Delay+25 Months
Predicted Overrun+₹1,042.16 Cr
Financial Status
Original Cost₹10,151.04 Cr
Revised Cost ₹55,548.87 Cr
Cumulative Expenditure₹27,961.55 Cr
x
50.3% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Significant Schedule Slip (+25 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+25 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.