Project ID: 705458Sector: Urban Development

Miyagam-Karjan-Dabhoi-Samlaya 96.46 km- Gauge conversion with electrification

Implementing Agency: CAOCWR WR mor
Project Overview
Core details and current status.
Agency
CAOCWR WR mor
State
Gujarat
Approval
01/2017 | (06/2026)
Target DoC
2026-12-01
Physical Progress
34%
x
Risk Assessment
79
High Risk
Predicted Delay+30 Months
Predicted Overrun+₹60.73 Cr
Financial Status
Original Cost₹483.88 Cr
Revised Cost ₹1,015.07 Cr
Cumulative Expenditure₹816.25 Cr
x
80.4% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Significant Schedule Slip (+30 Months)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+30 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.