Project Overview
Core details and current status.
Agency
CAOC/ER ER mor
State
Multi-States (Bihar, Jharkhand)
Approval
03/2014 | (04/2026)
Target DoC
2028-03-01
Physical Progress
40%
x
Risk Assessment
79
High RiskPredicted Delay+48 Months
Predicted Overrun+₹387.35 Cr
Financial Status
Original Cost₹2,555.00 Cr
Revised Cost ₹2,700.43 Cr
Cumulative Expenditure₹1,775.66 Cr
x
65.8% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Moderate Budget Utilization InefficiencyHistorically accounts for 30-40% of schedule deviations in similar Road Transport projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Road Transport projects.
- Extreme Schedule Delay Predicted (+48 Months)Historically accounts for 30-40% of schedule deviations in similar Road Transport projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+48 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.