Project ID: 619072Sector: Coal

Bangalore/TN border to Hoskote

Implementing Agency: NHAI
Project Overview
Core details and current status.
Agency
NHAI
State
Chhattisgarh
Approval
02/2022 | (02/2023)
Target DoC
2025-02-01
Physical Progress
94.89%
x
Risk Assessment
62
High Risk
Predicted Delay+13 Months
Predicted Overrun+₹125.84 Cr
Financial Status
Original Cost₹1,181.68 Cr
Revised Cost ₹1,297.76 Cr
Cumulative Expenditure₹1,153.14 Cr
x
88.9% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Coal projects.
  • Significant Schedule Slip (+13 Months)
    Historically accounts for 30-40% of schedule deviations in similar Coal projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+13 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.