Project Overview
Core details and current status.
Agency
NHAI
State
Uttar Pradesh
Approval
03/2018 | (02/2019)
Target DoC
2022-06-01
Physical Progress
100%
x
Risk Assessment
87
Critical RiskPredicted Delay+44 Months
Predicted Overrun+₹196.31 Cr
Financial Status
Original Cost₹1,226.64 Cr
Revised Cost ₹2,069.60 Cr
Cumulative Expenditure₹1,359.14 Cr
x
65.7% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Energy projects.
- Extreme Schedule Delay Predicted (+44 Months)Historically accounts for 30-40% of schedule deviations in similar Energy projects.
- Multiple Historical Bottlenecks Identified in RegionHistorically accounts for 30-40% of schedule deviations in similar Energy projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+44 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.