Project ID: 701167Sector: Roads & Highways

AIIMS Kashmir at Awantipora Jammu & Kashmir

Implementing Agency: PMSSY AND Institute of NATIONAL Importance
Project Overview
Core details and current status.
Agency
PMSSY AND Institute of NATIONAL Importance
State
Chhattisgarh
Approval
01/2019 | (03/2019)
Target DoC
2025-12-01
Physical Progress
79%
x
Risk Assessment
83
Critical Risk
Predicted Delay+34 Months
Predicted Overrun+₹241.49 Cr
Financial Status
Original Cost₹1,828.00 Cr
Revised Cost ₹2,570.19 Cr
Cumulative Expenditure₹1,602.61 Cr
x
62.4% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Roads & Highways projects.
  • Significant Schedule Slip (+34 Months)
    Historically accounts for 30-40% of schedule deviations in similar Roads & Highways projects.
  • Multiple Historical Bottlenecks Identified in Region
    Historically accounts for 30-40% of schedule deviations in similar Roads & Highways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+34 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.