Project ID: 705505Sector: Railways

Wardha-Nagpur - 4th line 78.70 km

Implementing Agency: CAOC/CR CR mor
Project Overview
Core details and current status.
Agency
CAOC/CR CR mor
State
Maharashtra
Approval
04/2017 | (06/2017)
Target DoC
2025-12-01
Physical Progress
88%
x
Risk Assessment
89
Critical Risk
Predicted Delay+48 Months
Predicted Overrun+₹133.04 Cr
Financial Status
Original Cost₹637.95 Cr
Revised Cost ₹1,194.59 Cr
Cumulative Expenditure₹1,090.49 Cr
x
91.3% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Extreme Schedule Delay Predicted (+48 Months)
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+48 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.