Project Overview
Core details and current status.
Agency
CAOC/CR CR mor
State
Maharashtra
Approval
04/2017 | (06/2017)
Target DoC
2025-12-01
Physical Progress
88%
x
Risk Assessment
89
Critical RiskPredicted Delay+48 Months
Predicted Overrun+₹133.04 Cr
Financial Status
Original Cost₹637.95 Cr
Revised Cost ₹1,194.59 Cr
Cumulative Expenditure₹1,090.49 Cr
x
91.3% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Railways projects.
- Extreme Schedule Delay Predicted (+48 Months)Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+48 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.