Project ID: 701391Sector: Road Transport

Aruna Medium Irrigation Project

Implementing Agency: Department of water resources-MH - II
Project Overview
Core details and current status.
Agency
Department of water resources-MH - II
State
Maharashtra
Approval
04/2009 | (01/2010)
Target DoC
2019-12-01
Physical Progress
100%
x
Risk Assessment
87
Critical Risk
Predicted Delay+25 Months
Predicted Overrun+₹25.57 Cr
Financial Status
Original Cost₹210.45 Cr
Revised Cost ₹1,472.14 Cr
Cumulative Expenditure₹1,734.71 Cr
x
117.8% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Road Transport projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Road Transport projects.
  • Significant Schedule Slip (+25 Months)
    Historically accounts for 30-40% of schedule deviations in similar Road Transport projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+25 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.