Sulwade-Jamphal-Kanoli Lift Irrigation Scheme

Implementing Agency: Department of water resources-MH - II
Project Overview
Core details and current status.
Agency
Department of water resources-MH - II
State
Maharashtra
Approval
04/2017 | (02/2019)
Target DoC
2023-06-01
Physical Progress
80.54%
x
Risk Assessment
85
Critical Risk
Predicted Delay+43 Months
Predicted Overrun+₹314.50 Cr
Financial Status
Original Cost₹2,407.67 Cr
Revised Cost ₹2,407.67 Cr
Cumulative Expenditure₹2,779.38 Cr
x
115.4% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
  • Extreme Schedule Delay Predicted (+43 Months)
    Historically accounts for 30-40% of schedule deviations in similar Railways projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+43 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.