Project ID: 400111Sector: Water Resources

Kelo Irrigation Project

Implementing Agency: Water Resources-CT
Project Overview
Core details and current status.
Agency
Water Resources-CT
State
Chhattisgarh
Approval
04/2008 | (04/2008)
Target DoC
2019-12-01
Physical Progress
73%
x
Risk Assessment
68
High Risk
Predicted Delay+28 Months
Predicted Overrun+₹38.25 Cr
Financial Status
Original Cost₹459.97 Cr
Revised Cost ₹727.04 Cr
Cumulative Expenditure₹620.15 Cr
x
85.3% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Water Resources projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Water Resources projects.
  • Significant Schedule Slip (+28 Months)
    Historically accounts for 30-40% of schedule deviations in similar Water Resources projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+28 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.