Project Overview
Core details and current status.
Agency
Talwara 29.16 km
State
Chhattisgarh
Approval
03/1983 | (04/1983)
Target DoC
2025-12-01
Physical Progress
84%
x
Risk Assessment
91
Critical RiskPredicted Delay+26 Months
Predicted Overrun+₹384.09 Cr
Financial Status
Original Cost₹2,018.00 Cr
Revised Cost ₹4,076.15 Cr
Cumulative Expenditure₹2,934.27 Cr
x
72.0% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Coal projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Coal projects.
- Significant Schedule Slip (+26 Months)Historically accounts for 30-40% of schedule deviations in similar Coal projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+26 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.