Project Overview
Core details and current status.
Agency
Rail Vikas Nigam Limited
State
Chhattisgarh
Approval
07/2009 | (11/2009)
Target DoC
2025-03-01
Physical Progress
98%
x
Risk Assessment
92
Critical RiskPredicted Delay+43 Months
Predicted Overrun+₹102.46 Cr
Financial Status
Original Cost₹1,516.45 Cr
Revised Cost ₹1,881.26 Cr
Cumulative Expenditure₹2,154.73 Cr
x
114.5% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
- Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Noticeable Cost Overrun TrajectoryHistorically accounts for 30-40% of schedule deviations in similar Urban Development projects.
- Extreme Schedule Delay Predicted (+43 Months)Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.
AI Prediction
+43 Months
This is the final forecast generated by our predictive engine.
How to read this chart:
Red bars push the prediction higher (increasing risk/delay/cost).
Green bars pull the prediction lower (mitigating risk).
Blue bar is the base historical average for all projects.