Project ID: 617374Sector: Urban Development

Dallirajhara - Rowghat New Rail Line Project, Phase-I

Implementing Agency: Rail Vikas Nigam Limited
Project Overview
Core details and current status.
Agency
Rail Vikas Nigam Limited
State
Chhattisgarh
Approval
07/2009 | (11/2009)
Target DoC
2025-03-01
Physical Progress
98%
x
Risk Assessment
92
Critical Risk
Predicted Delay+43 Months
Predicted Overrun+₹102.46 Cr
Financial Status
Original Cost₹1,516.45 Cr
Revised Cost ₹1,881.26 Cr
Cumulative Expenditure₹2,154.73 Cr
x
114.5% of Revised Cost Used
Primary Risk Drivers
Qualitative factors escalating risk.
  • Severe Financial-to-Physical Progress Mismatch (Fund Depletion Risk)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Extreme Schedule Delay Predicted (+43 Months)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
Predictive Analytics & Driver Explainability
Quantitative breakdown of the key factors driving this project's predicted outcome.

AI Prediction

+43 Months

This is the final forecast generated by our predictive engine.

How to read this chart:

Red bars push the prediction higher (increasing risk/delay/cost).

Green bars pull the prediction lower (mitigating risk).

Blue bar is the base historical average for all projects.