Thorapalli - Agraharam - Jittandahalli Section from km 23.350 to km 60.100 [Hosur to

619094
Project Overview
Core details and current status.
Implementing Agency
Dhamrapuri Pkg-2]
Location / State
Tamil Nadu
Date of Approval
02/2019 | (12/2021)
Original Target DoC
2023-12-01
Physical Progress
77.57%
x
Statistical Risk Assessment
87/100
Critical Risk
Predicted Delay+23 Months
Predicted Overrun+₹273.43 Cr
Financial Status
Original Cost₹1,243.57 Cr
Revised Cost ₹1,272.11 Cr
Cumulative Expenditure₹827.88 Cr
x
65.1% of Revised Cost
Predictive Insights & Risk Drivers
Key factors contributing to the Calculated Risk Score.
  • Noticeable Cost Overrun Trajectory
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Significant Schedule Slip (+23 Months)
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.
  • Multiple Historical Bottlenecks Identified in Region
    Historically accounts for 30-40% of schedule deviations in similar Urban Development projects.